Clausing Industrial, a manufacturer of machine tools, leased 71,750 square feet of office and warehouse space from Imperial Beverage. The $1.8 million project focused on converting an old interior rail dock into new office space and constructing a new pre-engineered metal building office addition. A fire-rated demising wall was also constructed to separate Clausing Industrial’s warehouse from Imperial Beverage’s adjacent warehouse spaces.
The design-build project also included the installation of an elaborate electrical system in the warehouse, rehabbing the existing parking lot and replacing an underground storm sewer system with a new overhead system.
Miller Davis self-performed selective demolition, concrete, structural steel and finish carpentry work.